Court setback pushes Keystone XL pipeline project deeper into limbo

FILE - In this March 11, 2013 photo, a sign reading

Enlarge Image

FILE - In this March 11, 2013 photo, a sign reading "Stop the Transcanada Pipeline" stands in a field near Bradshaw, Neb., along the Keystone XL pipeline route through the state. A Nebraska district court struck down a law that allowed the Keystone XL oil pipeline to proceed through the state, Wednesday, Feb. 19, 2014. The law could have been used to force landowners to allow the pipeline on their property. (AP Photo/Nati Harnik, File)

WASHINGTON - Not even the U.S. president can save the Keystone XL pipeline project now — at least not by himself.

The long-delayed plan suffered a major setback Wednesday when a Nebraska district judge ripped up a state law that could have forced landowners to allow the pipeline through their property.

The ruling opens up the prospect of more regulatory hurdles, complicated negotiations with landowners, legal fights and fresh delays, regardless of whether or not Barack Obama ever approves the controversial project.

Lancaster County Judge Stephanie Stacy declared unconstitutional a law that had given Nebraska Gov. Dave Heineman the power to push the project through private land.

Unless the law is reinstated by a higher court, Calgary-based pipeline builder TransCanada Corp. could be forced to either draw up a new route or seek permission from every last landowner on the current one.

Additional lawsuits seem almost inevitable in the ongoing fight over a project designed to increase the pipeline capacity for Canadian oil into the U.S. by about one-quarter — a pitched battle that has already lasted for years.

Stacy insisted her ruling had nothing to do with the merits of the pipeline and everything to do with Nebraska's constitution.

"TransCanada's Keystone XL pipeline has become a political lightning rod for both supporters and opponents of the pipeline, but the issues before this court have nothing to do with the merits of that pipeline," she wrote.

"The constitutional issues before this court will not require consideration of the current pipeline debate, nor will the decision in this case resolve that debate."

State officials who defended the law will appeal to the Nebraska Supreme Court. Nebraska lawmakers may have to pass a new pipeline-siting law to allow the third-party Public Service Commission to act.

If they do, it's not yet clear how long the five-member commission might take on the issue or whether it would approve the pipeline.

TransCanada, meanwhile, said it was disappointed and disagreed with the decision, but would analyze it before deciding on its next steps.

As it stands, TransCanada has settled with landowners in five of six U.S. states through which the pipeline is supposed to pass, as well as with more than two-thirds of the affected landowners in Nebraska.

But a minority have kept fighting, despite skyrocketing offers of compensation.

Jeanne Crumly and her husband have seen offers for use of their land surge from $8,900 to $61,977.84. But they don't want the pipeline on their family farm at any price.

Crumly, who lives in the tiny Nebraska town of Page, about 300 kilometres northwest of Omaha, said she had to read the ruling a couple of times to believe it. She made celebratory phone calls to her husband and children once it sank in.

"It felt great," Crumly said. "There's some justice and it's not just money running the show."

The company had been upping the ante for access to people's property, presumably to settle all possible disputes in the event Obama approved the pipeline.

TransCanada, which has complained it's been losing money as the pipeline equipment sits idle, had been hoping to start building during this year's construction season.

That plan now seems like a distant long shot.

The southern leg of the pipeline is already operational. But oil must still be transported by rail from Alberta through the northern U.S. before it can be sent by pipeline to refineries on the Gulf of Mexico.

The issue came up at a North American leaders' summit in Mexico, where Prime Minister Stephen Harper pressed Obama to provide some clarity on his intentions.

Officials said Obama's message remained unchanged: there's a regulatory process underway, and he doesn't control it.

There's a 90-day period during which U.S. government departments can raise concerns about the pipeline, before the State Department makes a final recommendation to the president.

However, administration officials have made it clear that there is no set deadline for either State or the president to make the final call.

Obama did add during a news conference later that he and Harper spoke about the need to work together on dealing with greenhouse-gas emissions.

There is some speculation in Washington that Obama might want to delay the politically sensitive decision until after November's midterm elections.

  • Rate this Rate This Star Icon
  • This article has not yet been rated.
  • We want you to tell us what you think of our articles. If the story moves you, compels you to act or tells you something you didn’t know, mark it high. If you thought it was well written, do the same. If it doesn’t meet your standards, mark it accordingly.

    You can also register and/or login to the site and join the conversation by leaving a comment.

    Rate it yourself by rolling over the stars and clicking when you reach your desired rating. We want you to tell us what you think of our articles. If the story moves you, compels you to act or tells you something you didn’t know, mark it high.

Sort by: Newest to Oldest | Oldest to Newest | Most Popular 0 Commentscomment icon

You can comment on most stories on brandonsun.com. You can also agree or disagree with other comments. All you need to do is register and/or login and you can join the conversation and give your feedback.

There are no comments at the moment. Be the first to post a comment below.

Post Your Commentcomment icon

Comment
  • You have characters left

The Brandon Sun does not necessarily endorse any of the views posted. Comments are moderated before publication. By submitting your comment, you agree to our Terms and Conditions. New to commenting? Check out our Frequently Asked Questions.

letters

Make text: Larger | Smaller

Brandon Sun Business Directory
Submit a Random Act of Kindness
Why Not Minot?
Welcome to Winnipeg

Social Media