Work at Brown Block site likely done by end of Nov.
Advertisement
Read this article for free:
or
Already have an account? Log in here »
We need your support!
Local journalism needs your support!
As we navigate through unprecedented times, our journalists are working harder than ever to bring you the latest local updates to keep you safe and informed.
Now, more than ever, we need your support.
Starting at $15.99 plus taxes every four weeks you can access your Brandon Sun online and full access to all content as it appears on our website.
Subscribe Nowor call circulation directly at (204) 727-0527.
Your pledge helps to ensure we provide the news that matters most to your community!
To continue reading, please subscribe:
Add Brandon Sun access to your Free Press subscription for only an additional
$1 for the first 4 weeks*
*Your next subscription payment will increase by $1.00 and you will be charged $20.00 plus GST for four weeks. After four weeks, your payment will increase to $24.00 plus GST every four weeks.
Read unlimited articles for free today:
or
Already have an account? Log in here »
Hey there, time traveller!
This article was published 01/11/2011 (5174 days ago), so information in it may no longer be current.
The city says it will be yet another week before the Brown Block is fully taken down, and another month before the mess is cleaned up.
The building, which originally collapsed in the early-morning hours of March 15, was the subject of a long three-way tug-of-war between the Winnipeg-based owners of the building, the owners of the next-door Strand Theatre and the city.
Endless delays seemed to come to an end with the announcement, in mid-September, that the parties had agreed on the construction of a wall to prevent the collapse of the Strand.
At that time, it was expected that demolition proper would begin within a couple of weeks, and the structure would be down by Halloween.
In a press release Monday afternoon, however, the city said that “hand demolition” is still underway, and that “machine demolition” was still to come.
City manager Scott Hildebrand said that the methodical nature of the work could sometimes precipitate delays. The building is now expected to be fully demolished by the end of the week.
From there, site cleanup and backfill will begin, and barring any unforeseen further delays, the city says the entire project should be wrapped up by the end of November.