Quebec environmental group denied court injunction against Northvolt EV battery plant

Advertisement

Advertise with us

MONTREAL - A Quebec Superior Court judge has refused to grant an injunction to halt tree cutting and other preparatory work at the site of a future electric vehicle facility east of Montreal.

Read this article for free:

or

Already have an account? Log in here »

We need your support!
Local journalism needs your support!

As we navigate through unprecedented times, our journalists are working harder than ever to bring you the latest local updates to keep you safe and informed.

Now, more than ever, we need your support.

Starting at $15.99 plus taxes every four weeks you can access your Brandon Sun online and full access to all content as it appears on our website.

Subscribe Now

or call circulation directly at (204) 727-0527.

Your pledge helps to ensure we provide the news that matters most to your community!

To continue reading, please subscribe:

Add Brandon Sun access to your Winnipeg Free Press subscription for only

$1 for the first 4 weeks*

  • Enjoy unlimited reading on brandonsun.com
  • Read the Brandon Sun E-Edition, our digital replica newspaper
Start now

No thanks

*$1 will be added to your next bill. After your 4 weeks access is complete your rate will increase by $4.99 a X percent off the regular rate.

Hey there, time traveller!
This article was published 26/01/2024 (602 days ago), so information in it may no longer be current.

MONTREAL – A Quebec Superior Court judge has refused to grant an injunction to halt tree cutting and other preparatory work at the site of a future electric vehicle facility east of Montreal.

Justice David Collier said today that the environmental group and the citizens who were seeking the order did not meet the high bar of evidence to show the province’s Environment Department and a municipality acted unreasonably in granting Northvolt a permit.

The Centre québécois du droit de l’environnement had sought an injunction suspending work on the 170-hectare site, arguing that the province allowed work to begin without proper analysis of the impact on the area’s biodiversity.

A Quebec Superior Court judge has refused to grant an injunction to halt tree cutting and other preparatory work at the site of a future electric vehicle facility southeast of Montreal. Security guards the entrance to the construction site of the new EV battery plant, Northvolt, in Saint-Basile-le-Grand, east of Montreal, Quebec, Friday, Jan. 19, 2024. THE CANADIAN PRESS/Christinne Muschi
A Quebec Superior Court judge has refused to grant an injunction to halt tree cutting and other preparatory work at the site of a future electric vehicle facility southeast of Montreal. Security guards the entrance to the construction site of the new EV battery plant, Northvolt, in Saint-Basile-le-Grand, east of Montreal, Quebec, Friday, Jan. 19, 2024. THE CANADIAN PRESS/Christinne Muschi

They also argued that the town of St-Basile-le-Grand — where the facility is to be partly located — gave a permit to cut down trees based on an “unreasonable interpretation” of rules protecting wetlands.

Collier wrote in his decision that governments have wide discretion when it comes to making decisions, and the court can only invalidate them in very limited circumstances.

He said the plaintiffs failed to demonstrate that the province was abdicating its responsibility or giving Northvolt a “blank cheque” to build the factory without a plan to remediate the environmental impacts.

This report by The Canadian Press was first published Jan. 26, 2024.

Report Error Submit a Tip

Business

LOAD MORE