Added lift station spending approved

Advertisement

Advertise with us

An additional $4 million will be spent from the city’s debenture for the southwest lift station project after Brandon City Council granted approval at its Monday meeting.

Read this article for free:


By clicking the button above, an account will be created and you will begin to receive some of our recommended newsletters. You may opt out of any newsletter by visiting your Email and Communication Preferences page or by clicking "unsubscribe" at the bottom of any email.

or

Already have an account? Log in here »

We need your support!
Local journalism needs your support!

As we navigate through unprecedented times, our journalists are working harder than ever to bring you the latest local updates to keep you safe and informed.

Now, more than ever, we need your support.

Starting at $15.99 plus taxes every four weeks you can access your Brandon Sun online and full access to all content as it appears on our website.

Subscribe Now

or call circulation directly at (204) 727-0527.

Your pledge helps to ensure we provide the news that matters most to your community!

To continue reading, please subscribe:

Add Brandon Sun access to your Free Press subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on brandonsun.com
  • Read the Brandon Sun E-Edition, our digital replica newspaper
Start now

*Your next Free Press subscription payment will increase by $1.00 and you will be charged $20.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

Hey there, time traveller!
This article was published 18/06/2024 (894 days ago), so information in it may no longer be current.

An additional $4 million will be spent from the city’s debenture for the southwest lift station project after Brandon City Council granted approval at its Monday meeting.

A report issued by city staff ahead of Monday’s meeting stated that the additional funds are needed to complete Phase 1 of the project and start work on the forcemains needed for Phase 2.

While council approved $30 million in borrowing in February 2023 for the project, a successful bylaw amendment from Coun. Shawn Berry (Ward 7) limited city administration to borrowing just $18 million before they had to return to council for further approval.

Brandon's general manager of development services, Mark Allard, said the city is still currently within its budget, but is expected to spend $35 million in total, which is $5 million over budget by the time the second lift station is done. (The Brandon Sun files)

Brandon's general manager of development services, Mark Allard, said the city is still currently within its budget, but is expected to spend $35 million in total, which is $5 million over budget by the time the second lift station is done. (The Brandon Sun files)

With that limit reached, staff returned for additional spending approval on Monday.

Phase 1 includes a new lift station at the corner of 34th Street and Patricia Avenue, a new gravity sewer for Brookwood South and the western half of the Bellafield neighbourhood, upgrades to the existing South End Lift Station and a new fibre optic communications network.

It is primarily intended to add wastewater utility capacity to those residential developments.

Phase 2, by comparison, is expected to add capacity for commercial development near the intersection of 18th Street and Patricia Avenue as well as future residential developments.

It will include the construction of a second lift station at 18th and Patricia, a gravity sewer for the eastern portion of Bellafield and future commercial developments and additional forcemains.

The staff report says that they have identified the construction of a dual forcemain servicing both phases as an opportunity to reduce costs and better align the work with future developments. To achieve that, they propose tendering both forcemains at the same time.

“Separating the efforts will lead to additional costs in mobilization, repeated construction efforts, and right of way restoration,” the report reads.

Ahead of Monday’s meeting, Brandon’s general manager of development services, Mark Allard, said that while the city’s purchasing website has yet to be updated with the winning bidder, the contract for the 34th Street lift station is being awarded to Surrey, B.C.-based contractor Industra Construction Corp at a value of $11,305,000.

During the meeting, Allard said that bid came in higher than the city’s initial estimate.

The new gravity sewer for the Brookwood/Bellafield neighbourhoods is being built by Waverly Developments, Allard said, with the $3,225,000 project being borne by both the developer and through the city’s development cost charges program. Those sewers would collect wastewater from those neighbourhoods and send them to the lift station.

However, since the city’s development reserve doesn’t have enough funds in it currently, the cost is being fronted through the $30-million debenture.

The cost for this work is valued at $14,530,000. Allard said he didn’t think either contract would require final approval from council.

For the dual forcemain, the cost is estimated to be around $5.6 million, and Allard said he expects the tender to be released within three to four weeks.

Should the forcemains be tendered separately, city staff expect the city to have to pay a premium of about 20 per cent, which would add a further $1.2 million to the cost.

The fibre optic work will be tendered separately, with a projected cost of $500,000.

Phase 1 of the project is expected to be built within 18 months and Phase 2 within two years.

Mayor Jeff Fawcett told his council colleagues that the city continues to lobby the provincial government for financial assistance with the project.

Earlier this year, Brandon and the Canada Infrastructure Bank entered into an agreement for a low-interest loan for this project and for water treatment plant upgrades expected to save the city around $1 million per year in borrowing costs.

Since 2022, the city has been working on updating its development cost charges, which are fees charged to developers as a contribution toward municipal infrastructure that their developments will eventually use.

The charges have not been substantially updated since they were introduced, except for some minor increases reflecting inflation.

Last December, a draft report from administration suggested that these fees be quadrupled.

However, Allard said in a pre-budget meeting in January that the city was reducing its proposal after a backlash from developers and representatives from the construction industry. The revised proposal would have seen the charges more than double from their previous amount.

Last month, the Brandon Downtown BIZ said it believed the city’s downtown core should be exempt from development cost charges as efforts to revitalize the neighbourhood continue.

On Monday, Allard told the Sun that administration was looking to come back to council with a final recommendation on changes to the program next month.

» cslark@brandonsun.com

» X: @ColinSlark

Report Error Submit a Tip