Hydro rebuts regulator on $3B turbine plan

Advertisement

Advertise with us

WINNIPEG — Manitoba Hydro is pushing back against the Public Utilities Board over the scope and expense of building electricity-generation capacity to meet the province’s future energy needs.

Read this article for free:


By clicking the button above, an account will be created and you will begin to receive some of our recommended newsletters. You may opt out of any newsletter by visiting your Email and Communication Preferences page or by clicking "unsubscribe" at the bottom of any email.

or

Already have an account? Log in here »

We need your support!
Local journalism needs your support!

As we navigate through unprecedented times, our journalists are working harder than ever to bring you the latest local updates to keep you safe and informed.

Now, more than ever, we need your support.

Starting at $15.99 plus taxes every four weeks you can access your Brandon Sun online and full access to all content as it appears on our website.

Subscribe Now

or call circulation directly at (204) 727-0527.

Your pledge helps to ensure we provide the news that matters most to your community!

To continue reading, please subscribe:

Add Brandon Sun access to your Free Press subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on brandonsun.com
  • Read the Brandon Sun E-Edition, our digital replica newspaper
Start now

*Your next Free Press subscription payment will increase by $1.00 and you will be charged $20.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

WINNIPEG — Manitoba Hydro is pushing back against the Public Utilities Board over the scope and expense of building electricity-generation capacity to meet the province’s future energy needs.

The Crown utility had proposed adding three 250-megawatt natural-gas combustion turbines to the two currently installed at its Brandon generating station at a $3-billion cost to taxpayers.

A PUB report made public Wednesday recommended that Hydro install one 250-megawatt generator instead but build the infrastructure to accommodate additional generators if and when they are required.

The Manitoba Hydro Brandon Generating Station. (Tim Smith/The Brandon Sun files)

The Manitoba Hydro Brandon Generating Station. (Tim Smith/The Brandon Sun files)

“Going with only one gas turbine initially could potentially impact our ability to support increased economic development, as well as slow the pace of electrification in Manitoba,” Hydro spokesperson Peter Chura said in an email Friday.

“As we have always said, our goal is to provide Manitobans with reliable, safe and affordable energy so we can keep the lights on, grow our economy, and support government policy objectives.”

The three-generator proposal raised concerns from environmental, Indigenous, consumer and seniors groups. The PUB, the quasi-judicial body that regulates utility rates, was asked to review the proposal.

The PUB agreed that a natural gas-powered turbine is critical to ensuring safe, reliable electricity during periods of peak demand.

“We believe our plan was the right one based on the information and factors we had available to us at the time we developed and submitted it,” Chura said.

Hydro’s load projections took into account the province’s policy objectives of increasing economic development as well as supporting increased electrification to meet net zero — the point where the amount of human-caused greenhouse gases released into the atmosphere equals the amount removed from it — by 2050 while balancing customer affordability, financial health, reliability and safety, Chura said.

“The load forecast used by the PUB in their recommendation does not contemplate meeting net zero by 2050 or consider provincial policy objectives of enhanced economic development. Ours did.”

Since then, Hydro has seen increased interest from U.S. utilities in extending or renewing major seasonal diversity contracts, he said. The utility makes capacity available to the U.S. in summer when energy demand there is high in exchange for American utilities making capacity available here in winter when demand is high.

“Those seasonal diversity exchanges may allow us to adjust our plan,” Chura said, adding the corporation would be looking at adjusting its combustion turbine plan even if the PUB had recommended proceeding with three, “as it could be a better option for Manitobans.”

“We are continuing our review of the PUB’s recommendations and will provide feedback to government by the end of December,” he said.

Premier Wab Kinew said Wednesday that he expected a response from Hydro by January, and that the government is also waiting for a PUB report on the power utility’s 10-year development plan before making a decision.

One of the environmental groups that took part in the public hearing process questions the government’s involvement.

“From our perspective, the way that the government has approached this particular project has been concerning,” said James Wilt, a spokesperson for Climate Action Manitoba.

In February 2025, Hydro submitted a preliminary project proposal for just two turbines to produce 500 megawatts, he said.

Eight months later, Kinew told reporters Manitoba planned to build more data storage infrastructure so people rely less on storage and cloud-computing services offered by Google, Microsoft and other U.S.-based companies.

“You’ll see servers and data centres in Manitoba in the future,” he told reporters at the time. “The idea is we need that capacity here at home to power the next generation of our Manitoba economy.”

A month later, the 2025 speech from the throne said Manitoba would build three power generators in Westman to produce 750 megawatts of electricity “to help heat our homes on the coldest days of the year.”

Kinew has since soured on data centres for Manitoba.

Wilt said he wants to know why that throne speech identifying the government’s priorities for the session called for more combustion generators than Manitoba Hydro initially proposed.

“The province, more or less, unilaterally announced that this plant would be expanded by 150 per cent, in terms of capacity,” he said Friday.

“From the get-go, we’ve certainly had concerns about the province.”

He said it is encouraging to hear the premier acknowledge the PUB’s role as an independent, quasi-judicial tribunal. The premier has praised the work of the board and its focus on what’s in the best interest of Manitoba ratepayers.

“We think that the PUB has done a really thorough and solid job,” he said, adding that Hydro has relied on outdated cost estimates for gas turbines.

“That’s of particular importance, because gas turbine costs have skyrocketed over the last year or two,” thanks mainly to the global demand for new AI data centres and generators to power them, he said.

“There’s a huge unresolved question as to how much these gas turbines are actually going to cost,” Wilt said.

» Winnipeg Free Press