VANCOUVER - A cryptocurrency firm has lost a bid to force BC Hydro to provide the vast amounts of power needed for its operations, upholding the provincial government's right to pause power connections for new crypto miners.

Read this article for free:

or

Already have an account? Log in here »

We need your support!
Local journalism needs your support!

As we navigate through unprecedented times, our journalists are working harder than ever to bring you the latest local updates to keep you safe and informed.

Now, more than ever, we need your support.

Starting at $15.99 plus taxes every four weeks you can access your Brandon Sun online and full access to all content as it appears on our website.

Subscribe Now

or call circulation directly at (204) 727-0527.

Your pledge helps to ensure we provide the news that matters most to your community!

To continue reading, please subscribe:

Add Brandon Sun access to your Winnipeg Free Press subscription for only

$1 for the first 4 weeks*

  • Enjoy unlimited reading on brandonsun.com
  • Read the Brandon Sun E-Edition, our digital replica newspaper
Start now

No thanks

*$1 will be added to your next bill. After your 4 weeks access is complete your rate will increase by $4.99 a X percent off the regular rate.

Hey there, time traveller!
This article was published 05/02/2024 (591 days ago), so information in it may no longer be current.

VANCOUVER – A cryptocurrency firm has lost a bid to force BC Hydro to provide the vast amounts of power needed for its operations, upholding the provincial government’s right to pause power connections for new crypto miners.

Conifex Timber Inc., a forestry firm that branched out into cryptocurrency mining, had gone to the B.C. Supreme Court to have the policy declared invalid.

But Justice Michael Tammen ruled Friday that the government’s move in December 2022 to pause new connections for cryptocurrency mining for 18 months was “reasonable” and not “unduly discriminatory.”

The Law Courts building, which is home to B.C. Supreme Court and the Court of Appeal, is seen in Vancouver, on Thursday, November 23, 2023. A cryptocurrency mining company has lost a bid to force BC Hydro to provide the vast amounts of power needed for its operations, upholding the provincial government's right to pause power connections for new crypto miners. THE CANADIAN PRESS/Darryl Dyck
The Law Courts building, which is home to B.C. Supreme Court and the Court of Appeal, is seen in Vancouver, on Thursday, November 23, 2023. A cryptocurrency mining company has lost a bid to force BC Hydro to provide the vast amounts of power needed for its operations, upholding the provincial government's right to pause power connections for new crypto miners. THE CANADIAN PRESS/Darryl Dyck

BC Hydro CEO Christopher O’Riley had told the court in an affidavit that the data centres proposed by Conifex would have consumed 2.5 million megawatt-hours of electricity each year.

That’s enough to power and heat more than 570,000 apartments, according to data on the power provider’s website.

Energy Minister Josie Osborne said when the policy was introduced that cryptocurrency mining consumes “massive amounts of electricity” by running high-powered computers around the clock, but adds “very few jobs” to the local economy.

In a statement released Monday, the company said it’s “disappointed” with the court’s ruling and is mulling an appeal.

“Conifex continues to believe that the provincial government is missing out on several opportunities available to it to improve energy affordability, accelerate technological innovation, strengthen the reliability and resiliency of the power distribution grid in British Columbia, and achieve more inclusive economic growth,” the statement said.

Before the provincial government paused new power connections for cryptocurrency miners, BC Hydro released a report outlining the “conundrum” they represent to the utility provider.

The report said power demand from cryptocurrency mining operations would challenge clean energy and electrification goals as adoption of things such as electric vehicles and heat pumps increase.

The report said bitcoin mining requires enough energy to power “a small country,” and moratoriums on crypto mining in China, Algeria and some U.S. states “created a significant increase in demand for power in B.C. by cryptocurrency mining operations.”

The court ruling said connection requests over the last few years from cryptocurrency miners in B.C. “far exceeded” BC Hydro’s projections.

It said the pause ordered by the government was in response to “the very real prospect that devoting such a large proportion of the available electrical power supply to one industry would leave less energy for other uses which might result in increased costs to all other residential and industry customers in B.C.”

This report by The Canadian Press was first published Feb. 5, 2024.