Diking efforts nearly complete in city
Advertisement
Read this article for free:
or
Already have an account? Log in here »
We need your support!
Local journalism needs your support!
As we navigate through unprecedented times, our journalists are working harder than ever to bring you the latest local updates to keep you safe and informed.
Now, more than ever, we need your support.
Starting at $15.99 plus taxes every four weeks you can access your Brandon Sun online and full access to all content as it appears on our website.
Subscribe Nowor call circulation directly at (204) 727-0527.
Your pledge helps to ensure we provide the news that matters most to your community!
To continue reading, please subscribe:
Add Brandon Sun access to your Free Press subscription for only an additional
$1 for the first 4 weeks*
- Enjoy unlimited reading on brandonsun.com
- Read the Brandon Sun E-Edition, our digital replica newspaper
*Your next Free Press subscription payment will increase by $1.00 and you will be charged $20.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.
Read unlimited articles for free today:
or
Already have an account? Log in here »
Hey there, time traveller!
This article was published 16/03/2011 (5648 days ago), so information in it may no longer be current.
Construction of earth dikes across Brandon is nearly complete.
City officials said 60,000 cubic metres of soil has been used so far to shore up the primary flood protection measure required, said Ian Christiansen, the city’s acting general manager of development services.
That construction has moved at a pace of approximately 3,000 cubic metres per day.
"Construction of the dike is on schedule," said Brian Kayes, Brandon’s emergency co-ordinator. "The river traditionally floods around mid-April to mid-May and it looks like we are on pace for something similar to that this year."
The dikes are being built to heights of 1183.6 feet above sea level at the First Street bridge, approximately two feet above the projected one-in-100-year flood crest expected on the Assiniboine River.
Dike construction is expected to reach completion in a matter of days.
The next provincial flood forecast will be on March 23.