Council moving forward on Sportsplex upgrades
Advertisement
Read this article for free:
or
Already have an account? Log in here »
We need your support!
Local journalism needs your support!
As we navigate through unprecedented times, our journalists are working harder than ever to bring you the latest local updates to keep you safe and informed.
Now, more than ever, we need your support.
Starting at $15.99 plus taxes every four weeks you can access your Brandon Sun online and full access to all content as it appears on our website.
Subscribe Nowor call circulation directly at (204) 727-0527.
Your pledge helps to ensure we provide the news that matters most to your community!
To continue reading, please subscribe:
Add Brandon Sun access to your Free Press subscription for only an additional
$1 for the first 4 weeks*
*Your next subscription payment will increase by $1.00 and you will be charged $20.00 plus GST for four weeks. After four weeks, your payment will increase to $24.00 plus GST every four weeks.
Read unlimited articles for free today:
or
Already have an account? Log in here »
Hey there, time traveller!
This article was published 21/01/2014 (4435 days ago), so information in it may no longer be current.
A recent audit of the Sportsplex pool has outlined the need to upgrade its mechanical systems to meet current Manitoba Health code requirements.
Council approved a recommendation last night to secure engineering services to begin the first step in the pool’s redevelopment at a cost of $286,300.
“To keep the Sportsplex pool open, we’ve been given directives from Manitoba Health that there’s certain things that we have to upgrade,” said Jeff Elliott, Sportsplex facility manager. “Water quality is the first item, the second is the pool air quality. There are new health codes regarding air quality so that’s something that really came to light later on.”
The recommendation council approved is to secure MCW/AGE Professional Engineers to prepare the mechanical drawings and specifications required to go out for tender.
Elliott provided a report to council following the 2013 audit. He said the best course of action, as agreed upon by the City of Brandon, Manitoba Health and the design engineering firm, is to replace the pool water circulation system, the pool air handling unit, tile the pool tank, install grating over the irregular pool edge and replace the bulkhead.
Elliott said in his report that the project “must move forward in a timely manner” for Manitoba Health to continue to support the operation of the Sportsplex pool.
In a letter to mayor and council, dated Dec. 6, 2013, Manitoba Health regional manager Stéfane Gravelle wrote that the department has noted water treatment and maintenance issues for some time.
“However, we have not required those upgrades to be undertaken because the future of the pool was undecided,” states the letter.
Now that it has been decided the facility will remain open, the city is expected to move forward in resolving issues. In 2011, city council passed a resolution to continue operating the Sportsplex. The facility was built in 1978 to host the 1979 Canada Winter Games.
“Manitoba Health is very happy with the way we run our facility right now,” Elliott said. “It is an old system so we’re mandated to monitor it closely and that’s fine, we can do that.”
Elliott stressed that there are no health concerns, as they submit monthly water samples.
“(Manitoba Health) is watching us very, very closely and that’s a good thing,” he said.
Some of the issues outlined in the Manitoba Health letter include the fact that there is degraded water quality because of the aging infrastructure and a lack of sufficient water recirculation, treatment and air ventilation rates; the current system can only maintain compliance with provincial disinfection standards approximately 25 per cent of the time; upgrades to the mechanical water and air handling systems are necessary to successfully resolve the violations and maintain the facility in a safe and satisfactory manner; and aging, damaged and/or deteriorating components of the basin need replacement.
The city is required to submit an upgrade plan to Manitoba Health no later than May 1. Once the current operating permit expires on May 31, new restrictions will be put in place at the Sportsplex.
“(The letter) did outline some very restrictive operating guidelines,” Elliott said. “This is showing that they are expecting the city to move forward, and do all the upgrades.”
Restrictions include: maximum bather load reduced from 355 to 200 persons, daily operating hours reduced from 16 to 10, water chemistry testing increased from one to two times per day to every two hours during hours of operation, among a few others.
Councillors discussed the need to seek provincial funding for the project, as it is a regional recreation facility.
Last month, council requested an update on the Sportsplex pool usage since the new Dood Cristall Family YMCA opened. According to the Sportsplex, they have seen growth in several programs, while showing a decrease in public swim attendance.
“Overall this report determined that the demand for aquatic space in Brandon is very strong and will support two pool facilities to serve the community and surrounding catchment area,” Elliott wrote in his report.
The estimated cost for total upgrades is $2.7 million.