New Neepawa hospital opening delayed

Advertisement

Advertise with us

The new Neepawa Health Centre — initially expected to welcome its first patients early next year — has had its opening delayed until late summer or early fall of 2027.

Read this article for free:


or

Already have an account? Log in here »

We need your support!
Local journalism needs your support!

As we navigate through unprecedented times, our journalists are working harder than ever to bring you the latest local updates to keep you safe and informed.

Now, more than ever, we need your support.

Starting at $15.99 plus taxes every four weeks you can access your Brandon Sun online and full access to all content as it appears on our website.

Subscribe Now

or call circulation directly at (204) 727-0527.

Your pledge helps to ensure we provide the news that matters most to your community!

To continue reading, please subscribe:

Add Brandon Sun access to your Free Press subscription for only an additional

$1 for the first 4 weeks*

  • Enjoy unlimited reading on brandonsun.com
  • Read the Brandon Sun E-Edition, our digital replica newspaper
Start now

*Your next Free Press subscription payment will increase by $1.00 and you will be charged $20.95 plus GST for four weeks. After four weeks, your payment will increase to $24.95 plus GST every four weeks.

The new Neepawa Health Centre — initially expected to welcome its first patients early next year — has had its opening delayed until late summer or early fall of 2027.

Prairie Mountain Health CEO Treena Slate confirmed the postponement on Wednesday, saying it would allow “appropriate time to onboard and train staff and familiarize teams with the new facility.”

The hospital, more than three times larger than the current facility, was first announced as a $127-million construction project in December 2021 by the former Progressive Conservative government, with a tentative completion date in 2025.

An aerial photo taken in June shows the progress of construction on the new Neepawa Health Centre, now set to open in mid to late 2027. (Supplied)

An aerial photo taken in June shows the progress of construction on the new Neepawa Health Centre, now set to open in mid to late 2027. (Supplied)

As of January, the hospital was reported to be 75 per cent completed with an anticipated opening date in early 2027, Prairie Mountain Health said at the time.

Darlene Jackson, president of the Manitoba Nurses Union, questions the reasons given by the health authority for the delay.

“I don’t know whether that is accurate about the training of the staff,” Jackson said Wednesday.

“I do not know why you would hold off opening a facility to train staff in an old facility,” she said. “Even if you don’t have enough staff to open every bed in the facility, you can move into it as you recruit staff.”

Once opened, the new Neepawa Health Centre will feature 60 acute beds — almost double the number of beds in the existing hospital — plus a larger emergency room, a hemodialysis suite and “enhanced space for a number of other programs,” the PMH website says.

Progressive Conservative MLA Jodie Byram, who represents the area, says she wants an opportunity to speak with hospital leadership about the delay.

“We’re already feeling and sensing exasperated resources at times, so having that delay is going to just maybe add a little bit more pressure,” she said Wednesday at an unrelated event in Carberry.

“We’ve seen the closure of Dauphin hospital and how the closure is affecting the patients in northern Manitoba. If (Neepawa) hospital was ready to go … it would have been an opportunity to have that patient caseload come to the new facility,” Byram said.

The opening of the new Portage la Prairie hospital, originally set for the fall, was delayed until spring of 2027 for the same reason, even though construction was completed this January.

Jackson said she thinks staff at both hospitals will be “extremely disappointed” by the delays.

“We hire new staff all the time and they’re trained … whether they’re in the old building or the new building,” she said. “That to me does not sound like a feasible reason.”

Health Minister Uzoma Asagwara did not grant an interview Wednesday, but provided an email statement.

“As construction progresses, we’re working with Prairie Mountain Health to recruit and train staff to ensure teams are familiar with the new space before welcoming patients,” the statement said.

Asagwara did not respond to questions about the current cost of the project or the staff training issues raised by Jackson.