Plenty of blame to go around for long-delayed $7B Hydro project

Advertisement

Advertise with us

Now that Manitoba Hydro has decided to proceed with a $7-billion plan to overhaul essential components of its two main transmission lines, the political blame game can start in earnest.

Read this article for free:

or

Already have an account? Log in here »

We need your support!
Local journalism needs your support!

As we navigate through unprecedented times, our journalists are working harder than ever to bring you the latest local updates to keep you safe and informed.

Now, more than ever, we need your support.

Starting at $15.99 plus taxes every four weeks you can access your Brandon Sun online and full access to all content as it appears on our website.

Subscribe Now

or call circulation directly at (204) 727-0527.

Your pledge helps to ensure we provide the news that matters most to your community!

To continue reading, please subscribe:

Add Brandon Sun access to your Winnipeg Free Press subscription for only

$1 for the first 4 weeks*

  • Enjoy unlimited reading on brandonsun.com
  • Read the Brandon Sun E-Edition, our digital replica newspaper
Start now

No thanks

*$1 will be added to your next bill. After your 4 weeks access is complete your rate will increase by $4.99 a X percent off the regular rate.

Opinion

Now that Manitoba Hydro has decided to proceed with a $7-billion plan to overhaul essential components of its two main transmission lines, the political blame game can start in earnest.

It’s not hard to see why the NDP government would be trying to hold the former Progressive Conservative government responsible for delaying investments in Bipoles I and II, which has driven up the total cost, amassed historic levels of debt and triggered unprecedented electricity rate hikes.

But is it a fair allegation? In politics, fair rarely has anything to do with it.

Hydro power lines are shown just outside Winnipeg on May 1, 2018. So, who's to blame for delaying much-needed work on two of the province's main transmission lines, thereby driving up the cost? (The Canadian Press)
Hydro power lines are shown just outside Winnipeg on May 1, 2018. So, who's to blame for delaying much-needed work on two of the province's main transmission lines, thereby driving up the cost? (The Canadian Press)

First, some background about what Hydro calls the HVDC (High Voltage Direct Current) Reliability Project.

Bipoles I and II — which carry 70 per cent of all electricity generated by Hydro — are both nearly 1,000 kilometres long.

The HVDC Project would see new converters and connectors replaced at both ends of those lines to turn alternating current (AC) from generating stations into direct current (DC) for transmission and then back to AC again when it reaches the end of the transmission lines near Winnipeg. This is needed to reduce the amount of electricity lost during transmission.

The HVDC project will cost at least $7 billion and require annual 3.5 per cent electricity rate hikes for at least 15 years. That’s a sobering reality that has the NDP government nervously twitching.

When asked by the Winnipeg Free Press about the project, Finance Minister Adrien Sala wasted little time assigning blame to the Tories, accusing the former government of failing “to make necessary investments to ensure continued reliability at Hydro.”

In pointing the long finger of blame, Sala is relying on the former PC government’s proven track record of deferring and delaying investments in health care, infrastructure and public sector contract settlements to improve its bottom line and pave the way for billions in tax cuts.

However, is this deferral of the much-needed replacement of HVDC equipment the latest example of the Tories kicking a costly can down the road?

Not necessarily.

According to Hydro, the HVDC equipment in question is now decades past its normal service life. Under normal circumstances, the converters and connectors have a roughly 35-year lifespan. Although converters on Bipole I are still within that best-before date, its connectors and the converters and connectors on Bipole II are way past the 35-year service life.

In other words, this has been a concern hovering over NDP and PC governments since at least the early 2000s.

Why didn’t those earlier governments get out ahead of the need to replace HVDC components? In short, both the NDP and Tories had other and — they would both argue — better things to do.

Between 1999 and 2016, NDP premiers Gary Doer and Greg Selinger were focused on adding additional generating capacity and building Bipole III, the much-needed third transmission line that runs down the west side of Lake Manitoba.

One could fairly argue the construction of Bipole III needed to be done before tackling HVDC concerns on Bipoles I and II. However, it’s impossible to ignore the fact the NDP knew the HVDC equipment was too old, and it still pushed the issue to the back burner. It was a decision that absolutely meant this project was going to become more costly.

And what of the Tories?

From 2016 to 2023, PC premiers Brian Pallister and Heather Stefanson had little interest in making new investments in Hydro.

Instead, they seized on every opportunity to assail the NDP government’s mishandling of the $5-billion Bipole III project. Pallister called Bipole III — which on the NDP’s watch ballooned to more than twice its original estimated cost — the greatest political scandal in Manitoba history.

The simple fact is that when you spend so much time protesting a $5-billion investment in a third transmission line, it’s politically impractical to simultaneously launch a $7-billion overhaul of the two oldest transmission lines.

It we take full account, how long have governments in this province been ignoring HVDC investments? That’s a really hard question to answer.

Hydro is taking a very politically cautious approach to that question.

The paper trail shows this issue was well known within both Hydro and government going back to the mid 2010s.

Officials from the Crown utility would only say that over the years, they have been “working on this issue at a lower level for a number of years” and performing “enhanced maintenance” to ensure the existing converters and connectors remained in service beyond their best-before dates.

At the same time, the officials said other major projects — the Manitoba-Minnesota transmission line, the Keeyask generating station and Bipole III — demanded Hydro’s full attention. This year was the first time Hydro included the HVDC project in its budget and rate application to the Public Utilities Board.

So, to whom should blame be assigned?

The fairest take is that successive governments, and Hydro itself, deferred work on the HVDC transmission system for a variety of reasons, leaving Manitoba vulnerable to a catastrophic interruption in power service.

Any time controversy erupts, politicians love to point fingers at other people. In this instance, however, every government of every stripe can share in the blame.

» Dan Lett is a Winnipeg Free Press columnist.